The grid organization did not complete the technological connection. Technical connection to electrical networks on a turnkey basis

The procedure for technological connection of power receiving devices to electrical networks is determined by the Federal Law, as well as the Rules for the technological connection of power receiving devices of electrical energy consumers, electrical energy production facilities, as well as electrical grid facilities belonging to network organizations and other persons, to electrical networks approved by the Decree of the Government of the Russian Federation Federation dated December 27, 2004 No. 861.

2. What is the procedure for concluding an agreement on technological connection to the electrical networks of UEC JSC?

To conclude an agreement, the applicant submits an application (in two copies) for technological connection if the Company’s power grid facilities are located at the shortest distance from the boundaries of your site. If at a distance of less than 300 meters (500 for rural areas) from its borders there are network facilities of several organizations, then you have the right to send an application to any of them. In order to obtain information about the electrical network company closest to your site, it is enough to send a request to the local government - all the necessary information must be provided to you within 15 working days.

The application shall indicate information in accordance with clause 9 of Section II of the Rules for the technological connection of power receiving devices of electrical energy consumers, electrical energy production facilities, as well as electrical grid facilities belonging to network organizations and other persons to electrical networks, approved by the Decree of the Government of the Russian Federation dated 12/27/2004 No. 861.

Next, we enter into an agreement with the applicant, which specifies the scope of construction and installation work required to be performed by the applicant and the network company. Afterwards, the parties, in accordance with the agreement, carry out a number of activities.

The next step is activation, during which the client receives and signs an act on the implementation of technological connection and acts of delimitation of balance sheet ownership and delimitation of operational responsibility.

The last step is to apply voltage. The actual reception of voltage and power is carried out subject to a concluded agreement with the sales organization.

3. How to apply for technological connection?

The application can be submitted in person at the Customer Service Center (115035, Moscow, Raushskaya embankment, 8 or sent by mail, .

4. What are the main requirements for the application and its completeness?

For a technological connection to the electrical networks of JSC UEC, it is necessary to fill out an application in accordance with clause 9 of the Rules for Technological Connection and attach a set of documents in accordance with clause 10 of the Rules for Technological Connection. Sample applications and their completeness can be found on the portal for technological connections.

5. How much does technological connection to electrical networks cost?

The fee for technological connection to the Company's networks of power receiving devices with a power of up to 15 kW (inclusive) is set based on the cost of technological connection activities, but not more than 550 rubles when connecting an applicant who owns objects classified as the third reliability category (for one source of power supply), provided that the distance from the boundaries of the applicant’s site to the electrical grid facilities of the voltage class required by the applicant of the network organization to which the application is submitted is no more than 300 meters in cities and towns and no more than 500 meters in rural areas.

The amount of payment for the technological connection of power receiving devices with a maximum power of over 15 kW is established by the Regional Energy Commission of Moscow in the territory of Moscow and by the Ministry of Economy of the Moscow Region in the territory of the Moscow region. For consumers with a power of up to 8900 kW at a voltage level below 35 kV, the fee for technological connection for 2015 was approved by the resolution of the Moscow Regional Energy Commission (543-tpe dated December 25, 2014).

For consumers with a power of over 8900 kW and a voltage level of over 35 kV, the fee for technological connection is approved on an individual project basis by the authorized executive body in the field of state regulation of tariffs (REC of Moscow).

6. How to re-issue documentation confirming technological connection?

The rules determine the list of persons and objects subject to this regulation. Among them:

  • facilities engaged in the production of electricity,
  • objects belonging to electrical network facilities,
  • devices that receive electricity for consumer needs.

These Rules have the force of law and are approved by decree of the Government of Russia and it applies to those cases when the following occurs:

  • energy receiving devices of new facilities put into operation;
  • energy receiving facilities in which, for technical reasons, the following indicators of the level of reliability of electricity supply, connection points, and production methods have been changed. At the same time, changes appeared in the facility’s power supply circuit, although this did not lead to changes in the increase or decrease in permissible power.

Technological connection- a mandatory condition for connecting electricity to the consumer

Connecting electricity to the consumer becomes possible only after such a mandatory procedure as technological connection- and all electrical appliances and equipment are subject to it. It is worth noting that such work must be carried out in accordance with the regulations specified in the current regulations and carried out by qualified companies. Unauthorized connection is illegal and can have serious consequences for the offender. Let's look at all the intricacies of technological connection.

What is technological

According to current government rules, such a thing as technological connection to electrical networks is a set of measures aimed at supplying electricity to consumer equipment from electrical networks. This procedure is carried out not only for new energy-receiving devices, but also for those whose technical characteristics have been changed (this could be changes in power supply circuits or a change in connection points).

In what cases is it not necessary to repeat connection to electrical networks

When an object that is already a registered consumer of electrical energy changes its owner, then connection to electrical networks not required if two conditions are met:

  • the previous owner made an authorized connection of all energy equipment in accordance with the current regulations;
  • the new owner’s activities do not require changes to the facility’s electricity supply schemes.

In this case, the new owner must notify the network organization supplying electricity about the transfer of ownership rights to this facility.

How is technological connection to electrical networks

As a rule, the process connection procedure is carried out in five stages:

  1. Application for connection to electrical networks.
  2. An agreement is concluded, to which technical conditions are attached.
  3. The parties to the agreement fulfill all its terms.
  4. Based on the results of the merger, all necessary acts are drawn up.
  5. An object connected to the power grid receives permission to operate.

All of the above activities are regulated by relevant government regulations.

Why is it so important to consider

If you want to connect an object to the power supply system, you will have to take everything into account rules for technological connection to electrical networks- only in this case the connection will have legal grounds. The professionals of the Center for Energy Solutions and Innovations (http://website) will not only help you understand all the nuances of this procedure, but will also perform all the necessary work with high quality

Having extensive experience as a contractor of PJSC MOESK (formerly OJSC MOESK) and knowing all the bureaucratic procedures inherent in the system of the former Mosenergo, we know how to solve any of your problems in the field of electricity supply.

We offer the following consulting services in the field of electrical energy:

  • comprehensive customer support in the process of connecting electricity (submitting an application for technological connection to electrical networks, receiving an Agreement and Technical Conditions (TS), fulfilling the requirements of the TS, submitting the TS, receiving acts, concluding an agreement with Mosenergosbyt);
  • adjustment of technical conditions(selection of optimal connection points, change in reliability category, change in power, etc.);
  • adjustment of the technological connection agreement(reduced cost, reduced time);
  • control and minimization of deadlines implementation of technological connection activities carried out by MOESK;
  • delivery of electrical installations inspectors of MOESK (ISS, Energouchet), OEK, Rostekhnadzor;
  • energy lawyer(settlement of any issues with inspectors of MOESK, OEK, Rostechnadzor, etc.);
  • obtaining an admission certificate electrical installations into operation in Rostekhnadzor (required for electrical installations of the 2nd reliability category from 150 kW);
  • and many other services, allowing you to save your money.

TECHNICAL CONNECTION TO ELECTRICAL NETWORKS “TURNKEY”

Comprehensive service for connecting the client to electrical networks: from collecting documents and submitting an application for connection to supplying voltage and concluding an energy supply agreement.

MORE ABOUT TECHNICAL CONNECTION

Connection to the electrical networks of PJSC "MOESK" is a complex process consisting of many stages:
1. Collection of documents and submission of an application for technological connection of new capacities (or to increase existing capacity).
2. Receipt of the draft technical specifications (technical conditions) and offer of an agreement for technological connection to the networks of PJSC "MOESK". THIS IS THE FIRST IMPORTANT POINT! It is necessary to monitor the technical specifications and assess the possibility of their adjustment (changes in technical conditions regarding connection points, reliability categories, etc.).
3. Monitoring the correct application of the tariff (fee for technological connection) IS THE SECOND IMPORTANT POINT. The cost of the technical connection contract and, accordingly, your costs directly depend on the correct application of the tariff.
4. Signing of the TP agreement.
5. Electrical installation design.
6. Coordination of the electrical installation project in the MKS RER, in EnergoUchet, in RosTechNadzor.
7. Execution of technical specifications (installation of electrical installations in accordance with technical conditions and design). 8. Handover of the electrical installation to the commission of PJSC “MOESK” - inspectors of RER MKS/Energouchet (and/or “MosEnergoSbyt”).
9. Signing an act on the fulfillment of technical conditions, an act on the implementation of technical connection and ARBPiEO (delimitation act).
10. Handing over the electrical installation to the inspector of RosTechNadzor (for subscribers connected to the second category of power supply reliability, this is necessary).
11. Obtaining a Certificate of Approval of the electrical installation for operation (Rostechnadzor).
12. Actual voltage supply.
13. Conclusion of an energy supply agreement (MosEnergoSbyt).

The Elektroset group of companies is ready to offer the implementation of any of these stages or COMPLETION OF THE ENTIRE COMPLEX “TURNKEY”.

OBTAINING A CERTIFICATE OF AUTHORIZATION OF THE ELECTRICAL INSTALLATION FOR OPERATION

Obtaining an admission certificate from Rostechnadzor is necessary to supply voltage to the electrical installations of subscribers connected under the second category of power supply reliability.

MORE ABOUT THE ACT OF ADMISSION

Subscribers connected to electrical networks in the second reliability category, if the power of their electrical installation is 150 kW or higher, must provide the network organization with an Electrical Installation Approval Certificate for Operation, obtained from RosTechNadzor, to supply voltage. To receive such a certificate, the subscriber must:
1. Coordinate with Rostechnadzor the internal power supply project.
2. Provide your person in charge of electrical facilities and his deputy, who have an electrical safety clearance group of at least 4.
3. Present the fully assembled electrical installation (from the point of connection to the terminal devices) for inspection by the inspector.
4. Provide a technical report on laboratory tests of electrical equipment included in the electrical installation.
Only a very good specialist can hand over an electrical installation to Rostechnadzor without any comments. Even if at first glance the electrical installation complies with all PUE standards, the Rostechnadzor inspector will definitely find violations that will allow him not to issue an admission certificate immediately, but to insist on a repeat visit. All repeat visits by the Rostechnadzor inspector are paid.

The Elektroset group of companies is ready to offer its services for handing over electrical installations to Rostechnadzor inspectors and handing over your electrical installation in one inspector visit, reducing your time and financial costs.

CONCLUSION OF AN ENERGY SUPPLY AGREEMENT WITH PJSC MOSENERGOSBYT

An agreement with a sales organization (in Moscow this is PJSC Mosenergosbyt) must be concluded no later than 60 days from the moment the meters are sealed and the electrical installation is turned on, otherwise the subscriber faces a fine for non-contractual/unaccounted use of electricity). We will collect all the necessary documents and conclude an energy supply agreement with Mosenergosbyt PJSC on your behalf.

COST OF CONSULTING SERVICES:

Service:

Description:

Price:


Consultation (in person in our office or by phone)

For any questions related to power supply

For free


On-site consultation at the Customer's site

Inspection of the customer’s facility for a more complete assessment of the situation and consultation. The cost of departure in Moscow is indicated


Technological connection

Collecting documents, submitting an application, obtaining technical specifications and a technical connection agreement, obtaining ARBPiEO acts, a technical connection act, a metering device approval act

For free*


Minimizing the Client's expenses for technological connection

Obtaining optimal specifications and technical connection agreements with a minimum tariff

Negotiable, 50% of the Client's savings


Redistribution, re-registration, confirmation of capacity

Submitting an application, obtaining technical specifications and ARBPiEO


From the explanations on technological connection to electrical networks “Methodological manual for entrepreneurs”. FAS Russia, OPORA Russia 2009

Terms and Definitions

« consumers of electrical energy» - persons purchasing electrical energy for their own household and (or) production needs;
« network organizations» - organizations that own, by right of ownership or on another basis established by federal laws, electrical grid facilities, with the use of which such organizations provide services for the transmission of electrical energy and carry out, in the prescribed manner, the technological connection of power receiving devices (power installations) of legal entities and individuals to electrical networks ;
« act of delimitation of balance sheet ownership of electric networks" - a document drawn up in the process of technological connection of energy receiving devices (power installations) of individuals and legal entities to electrical networks, defining the boundaries of balance sheet ownership;
« act of delimitation of operational responsibilities of the parties" - a document drawn up by the network organization and the consumer of services for the transmission of electrical energy in the process of technological connection of power receiving devices, defining the boundaries of responsibility of the parties for the operation of the corresponding power receiving devices and power grid facilities;
« balance sheet limit" - the line for dividing electric power facilities between owners on the basis of ownership or possession on another basis provided for by federal laws, defining the boundary of operational responsibility between the network organization and the consumer of electric energy transmission services (the consumer of electric energy in whose interests an agreement on the provision of electric energy transmission services is concluded energy) for the condition and maintenance of electrical installations;
« point of connection to the electrical network" - the place of physical connection of the power receiving device (power installation) of the consumer of electric energy transmission services (electric energy consumer in whose interests an agreement on the provision of electric energy transmission services is concluded) with the electrical network of the network organization.

3. General provisions

3.1. The process connection procedure is carried out when connecting power receiving devices that are being put into operation for the first time, previously connected and being reconstructed, the connected power of which is increasing, as well as in cases in which the category of reliability of power supply, connection points, and types of production activities that do not entail a revision change in relation to previously connected power receiving devices. values ​​of connected power, but changing the external power supply scheme of such power receiving devices.
3.2. Technological connection is carried out on a reimbursable basis on the basis of an agreement concluded between the network organization and a legal or individual person.
3.3. Technological connection is a complex procedure, the stages of which are:
1) filing an application for technological connection;
2) conclusion of an agreement for technological connection;
3) implementation by the parties to the agreement of the activities provided for in the agreement;
4) obtaining permission from Rostechnadzor to allow the applicant’s facilities into operation;
Attention! Obtaining permission from Rostechnadzor to allow the facility to operate is not required for:
- facilities of legal entities or individual entrepreneurs with a capacity of up to 100 kW inclusive;
- objects of individuals with a power of up to 15 kW inclusive (for domestic needs);
- temporary connection of facilities with a power of up to 100 kW inclusive.

5) the network organization actually connects the applicant’s facilities to electrical networks;
6) actual reception (supply) of voltage and power (fixation of the switching device in the “on” position);
7) drawing up an act on technological connection and an act of delimitation of balance sheet ownership and operational responsibility.
3.4. The grid organization is obliged to carry out technological connection measures in relation to any person who applies to it, provided that he complies with the Rules for Technological Connection.
The conclusion of an agreement is mandatory for a network organization. In the event of an unjustified refusal or evasion by a network organization from concluding a contract, the interested party has the right to file a claim in court to compel the conclusion of the contract and to recover damages caused by such an unjustified refusal or evasion. Also, in such a situation, the applicant has the right to contact the antimonopoly authority with a statement to initiate a case for violation of antimonopoly legislation.
Attention! The grid organization does not have the right to refuse the applicant to make a technological connection due to its lack of technical capabilities. The legislation in the electric power industry does not provide such grounds for refusal of technological connection.
The rules for technological connection establish only the specifics of the technological connection procedure for certain categories of consumers in the absence of the technical capability of the network organization.
If there is no technical possibility:
- in relation to facilities of legal entities or individual entrepreneurs with a power of up to 100 kW inclusive, as well as facilities of individuals with a power of up to 15 kW inclusive (for domestic needs), the grid organization is obliged to carry out measures for technological connection in the general manner, as well as if technically possible;
- in relation to other objects, the network organization is obliged, within 30 days after receiving the application, to contact the authorized executive body in the field of state regulation of tariffs (hereinafter referred to as the regulatory body) to calculate the fee for technological connection for an individual project.
If the applicant agrees to make payments for technological connection for an individual project in the amount determined by the regulatory body, the network organization does not have the right to refuse to conclude the agreement. The network organization has the right to refuse to conclude an agreement in the absence of technical feasibility if the applicant does not agree to technological connection at the fee determined by the regulatory body.
3.5. The time frame for technological connection cannot exceed:
- 15 working days (unless a longer period is specified in the application) - for applicants for temporary (for a period of no more than 6 months) technological connection, if the distance from the applicant’s power receiving device to existing electrical networks of the required voltage class is no more than 300 meters ;
- 6 months – for legal entities whose connected power does not exceed 100 kW and individuals, in the case of technological connection to electrical networks with a voltage class of up to 20 kV inclusive, if the distance from existing electrical networks of the required voltage class to the boundaries of the applicant’s plot on which they are located connected power receiving devices, is no more than 300 meters in cities and towns and no more than 500 meters in rural areas;
- 1 year - for applicants whose total connected capacity of power receiving devices does not exceed 750 kVA, unless shorter periods are provided for by the relevant investment program or agreement of the parties;
- 2 years - for applicants whose total connected capacity of power receiving devices exceeds 750 kVA, unless other periods (but not more than 4 years) are provided for by the relevant investment program or agreement of the parties.
Attention! The technological connection procedure is one-time:
- the fee for technological connection is charged once;
- when changing the form of ownership or owner (applicant or network organization), a new technological connection procedure is not required;
- a change in the form of ownership or owner (applicant or network organization) does not entail re-payment for technological connection.

4. Submitting an application for technological connection

4.1. When deciding which network organization to apply for technological connection to, you should pay attention to the distance from the boundaries of the applicant’s site to the nearby power grid facilities of the network organization.
The distance from the borders of the applicant's site to the power grid facilities of the network organization means the minimum distance measured in a straight line from the border of the site (location of connected power receiving devices) of the applicant to the nearest power network facility (power line support, cable line, switchgear, substation) having voltage class specified in the application, existing or planned for commissioning in accordance with the investment program of the network organization, approved in the prescribed manner, and within the time limits established for technological connection (see clause 3.5).
If at a distance of less than 300 meters from the boundaries of the applicant’s site there are power grid facilities of several network organizations, the applicant has the right to send an application to any of them. This rule does not apply to applicants who intend to carry out technological connection of power receiving devices according to an individual project.
If there is only one network organization at a distance of less than 300 meters from the boundaries of the applicant’s site, the applicant sends the application to this network organization.
If all power grid facilities of all network organizations are located at a distance of 300 meters or more from the boundaries of the site, the applicant must send an application for concluding an agreement to the network organization whose power grid facilities are located at the shortest distance from the boundaries of the applicant’s site.
Attention! The requirements of the network organization that the applicant independently resolve issues related to indirect connection (i.e., connection to the electrical networks of third parties) are unfounded. The grid organization is obliged to resolve issues with the owner of the electric grid facilities through whose facilities the indirect connection will be carried out.
4.2. The application is sent by the applicant to the network organization in 2 copies by letter with a list of attachments. The applicant has the right to submit an application through an authorized representative, and the network organization is obliged to accept such an application.

5. Requirements for the content of the application for technological connection. Completeness of documents

5.1. The application for technological connection of facilities of individuals with a power of up to 15 kW inclusive (for domestic needs) must indicate:
a) last name, first name and patronymic of the applicant, series, number and date of issue of passport or other identity document;
b) place of residence of the applicant;
c) the name and location of power receiving devices that need to be connected to the electrical networks of the network organization;

e) maximum power of the applicant’s energy receiving devices.

5.2. The application for technological connection of facilities of legal entities or individual entrepreneurs with a capacity of up to 100 kW inclusive must indicate:
a) details of the applicant (for legal entities - full name and entry number in the Unified State Register of Legal Entities (USRLE), for individual entrepreneurs - entry number in the Unified State Register of Individual Entrepreneurs (USRIP) and the date of its entry into the register, for individuals - last name, first name, patronymic, series, number and date of issue of passport or other identity document);


d) timing of the design and phased commissioning of energy receiving devices (including by stages and queues);
e) phased distribution of power, commissioning dates and information about the category of reliability of power supply when commissioning power receiving devices in stages and queues.


h) proposals for the payment procedure and terms of payment in installments for technological connection - for applicants whose maximum power of power receiving devices is over 15 and up to 100 kW inclusive.

5.3. An application for technological connection of facilities of legal entities or individual entrepreneurs, the total connected power of power receiving devices of which does not exceed 750 kVA, must indicate:

b) the name and location of power receiving devices that need to be connected to the electrical networks of the network organization;
c) location of the applicant;
d) the number of connection points indicating the technical parameters of the elements of power receiving devices;
e) the declared level of reliability of power receiving devices;
f) time frames for the design and phased commissioning of power receiving devices (including by stages and queues);
g) phased distribution of power, commissioning dates and information about the category of reliability of power supply when commissioning power receiving devices in stages and queues.
h) maximum power of the applicant’s energy receiving devices;
i) nature of the load (type of production activity).

5.4. An application for a temporary (for a period of no more than 6 months) technological connection to provide electrical energy to mobile objects with a maximum power of up to 100 kW inclusive, must indicate:
a) details of the applicant (for legal entities - full name and entry number in the Unified State Register of Legal Entities, for individual entrepreneurs - entry number in the Unified State Register of Legal Entities and the date of its entry into the register, for individuals - last name, first name, patronymic, series, number and date of issue of the passport or other identification document);
b) the name and location of power receiving devices that need to be connected to the electrical networks of the network organization;
c) location of the applicant;
d) timing of the design and phased commissioning of energy receiving devices (including by stages and queues);
e) phased distribution of power, commissioning dates and information about the category of reliability of power supply when commissioning power receiving devices by stages and queues;
f) maximum power of the applicant’s connected power receiving devices;
g) the nature of the load (type of economic activity of the economic entity);
h) term of temporary accession.

5.5. The application of other consumers shall indicate:
a) details of the applicant (for legal entities - the full name and entry number in the Unified State Register of Legal Entities, for individual entrepreneurs - the entry number in the Unified State Register of Individual Entrepreneurs and the date of its entry into the register, for individuals - last name, first name, patronymic, series, number and date of issue of the passport or other identification document);
b) the name and location of power receiving devices that need to be connected to the electrical networks of the network organization;
c) location of the applicant;
d) maximum power of energy receiving devices and their technical characteristics, number, power of generators and transformers connected to the network;
e) the number of connection points indicating the technical parameters of the elements of power receiving devices;
f) the declared level of reliability of power receiving devices;
g) the declared nature of the load (for generators - the possible speed of increasing or decreasing the load) and the presence of loads that distort the shape of the electric current curve and cause voltage asymmetry at the connection points;
h) the value and justification of the value of the technological minimum (for generators), technological and emergency armor (for consumers of electrical energy);
i) terms of design and phased commissioning of power receiving devices (including by stages and queues);
j) phased distribution of power, commissioning dates and information about the category of reliability of power supply when commissioning power receiving devices in stages and queues.

Attention! The network organization has no right to require the applicant to provide any other information, and the applicant is not obliged to provide any other information.
5.6. The following documents are attached to the application:
a) a plan for the location of power receiving devices that need to be connected to the electrical networks of the network organization;
b) single-line diagram of the applicant’s electrical networks connected to the electrical networks of the network organization, the rated voltage class of which is 35 kV and above, indicating the possibility of redundancy from its own power supply sources (including redundancy for its own needs) and the possibility of switching loads (generation) via internal networks the applicant;
c) list and power of energy receiving devices that can be connected to emergency automatic devices;
d) a copy of a document confirming the ownership or other basis provided by law for the capital construction project and (or) the land plot on which the applicant’s objects are (will be located), or the right of ownership or other basis provided by law for power receiving devices;
e) power of attorney or other documents confirming the authority of the applicant’s representative submitting and receiving documents, if the application is submitted to the network organization by the applicant’s representative;
f) forms of modular schemes for technological connection of power receiving devices, approved by the Ministry of Energy of the Russian Federation - only for facilities of legal entities and individual entrepreneurs with a power of up to 100 kW inclusive, facilities of individuals up to 15 kW inclusive (for domestic needs).
Attention! The network organization does not have the right to require the applicant to submit any other documents, and the applicant is not obliged to submit any other documents.

Special attention! The forms of modular grid connection schemes are currently not approved by the Ministry of Energy of the Russian Federation. Consequently, the network organization does not have the right to require applicants to submit modular diagrams for technological connection before they are approved by the Ministry of Energy of the Russian Federation, and the applicant is not obliged to submit modular diagrams. Failure by the applicant to submit a modular diagram cannot be grounds for the grid organization’s refusal to accept the application and conclude a technological connection agreement.



<...>
6. Conclusion of an agreement on technological connection
7. Contents and validity period of technical specifications
<...>

8. Fee for technological connection and payment procedure

8.1. The fee for technological connection of power receiving devices with a maximum power not exceeding 15 kW inclusive (taking into account the power previously connected at a given connection point) is established based on the cost of technological connection activities in the amount of no more than 550 rubles (clause 71 of the Pricing Fundamentals).
8.2. If the applicant is a non-profit organization for the supply of electricity to citizens - members of this organization, who pay using a common meter at the input, the applicant's payment to the network organization should not exceed 550 rubles multiplied by the number of members (subscribers) of this organization, provided that each member of this organization joins no more 15 kW.
Non-profit organizations that are subject to this rule include:
- horticultural, vegetable gardening or dacha non-profit associations of citizens (gardening, vegetable gardening or dacha non-profit partnership, horticultural, vegetable gardening or dacha consumer cooperative, horticultural, vegetable gardening or dacha non-profit partnership) - non-profit organizations established by citizens on a voluntary basis to assist its members in solving common problems social and economic tasks of gardening, vegetable gardening and dacha farming (hereinafter referred to as a horticultural, vegetable gardening or dacha non-profit association), combined household buildings of citizens (cellars, sheds and other structures), calculated using a common meter at the input;
- religious organizations maintained at the expense of parishioners;
- garage construction, garage cooperatives, parking lots, calculated using a common meter at the input, if, by decision of the regulatory body and issued by a separate decision, these consumers are assigned to the “Population” tariff group.
8.3. For other applicants, the amount of payment for technological connection is determined in accordance with the decision of the regulatory body.
8.4. For applicants - legal entities with connected capacity of facilities over 15 to 100 kW inclusive, the payment procedure is established as follows:
- 15 percent of the fee is paid within 15 days from the date of conclusion of the contract;
- 30 percent of the fee is paid within 60 days from the date of conclusion of the agreement, but not later than the date of actual accession;
- 45 percent of the fee is paid within 15 days from the date of signing by the parties of the act on the applicant’s fulfillment of the technical conditions, the act on the inspection of metering devices and the approval of the calculation scheme for metering electrical energy (power), as well as the act on the delimitation of the balance sheet ownership of electrical networks and the act on the delimitation of operational liability of the parties;
- 10 percent of the fee is paid within 15 days from the date of actual joining.
At the same time, for small and medium-sized businesses, the agreement (at the request of such applicants) provides for an interest-free installment payment in the amount of 95 percent of the payment for technological connection with the condition of quarterly payment of the payment in equal shares of the total installment amount for a period of up to 3 years from the date the parties sign the act on implementation of technological connection.
For other groups of consumers, the payment procedure is established by the terms of the contract.

<...>
9. Finalization of the technological connection process
10. Disclosure by grid organizations of information on the implementation of technological connection
<...>

11. Answers to frequently asked questions about technological connection problems

1. Question: I submitted documents to connect my house to the electrical grid to the Network Organization. After 2 weeks, we were informed that our documents had been sent to a Private Network Company, but there were no lines from the Network Organization in our area. The Private Network Company charges a huge amount of money for connecting a house to a power line for each connected kW and increases the tariffs for paying for electrical energy. What should we do in this situation?
Answer: You need to determine the distance from the boundaries of your land plot to the nearest power grid facility of the Grid organization. If this distance is 300 meters or more, then the Network Organization did the right thing. If the distance is less than 300 meters, then the Network organization unreasonably avoids concluding an agreement with you and you have the right to appeal its actions in the prescribed manner.
A private network organization does not have the right to independently determine the cost of technological connection to its electrical networks, as well as the cost of services for the transmission of electrical energy through its networks. These tariffs are subject to state regulation and their amounts are established by government bodies authorized to regulate tariffs. Moreover, if the power you declare is up to 15 kW inclusive, the cost of technological connection for you should not exceed 550 rubles.
If a private network organization independently determines the cost of technological connection and prices for electric energy transmission services, it violates the law, including antimonopoly law. You have the right to appeal the actions of the Private Network Organization in accordance with the established procedure.

2. Question: I submitted an application for technological connection to electrical networks to the Network Organization. Due to the lack of response from the Network Organization, I wrote a letter to the Network Organization with a complaint about the delay in the procedure for drawing up the contract. In response to the complaint, I received a letter with an offer to enter into an agreement with a suspensive condition, according to which the implementation of measures by the Grid organization will be carried out within 6 months from the date of entry into force of the regulatory act of the executive authority in the field of tariff regulation, including the shortfall in income of the network organization from connection power receiving devices with a maximum power not exceeding 15 kW inclusive, in the tariff for the provision of services for the transmission of electrical energy.
Answer: This is a gross violation on the part of the Network organization. The grid organization is obliged to conclude an agreement with you and carry out measures for technological connection within the established time frame, regardless of when the decision of the regulatory body on compensation for the outstanding expenses of the Grid organization is made and comes into force.

3. Question: I submitted an application to the Network Organization, received an agreement on technological connection and technical conditions. Due to the fact that the agreement did not comply with the Technological Connection Rules, I sent a request to the Network Organization to correct this agreement and bring it into compliance with the law. To which I received a verbal refusal. Are the actions of the Network Organization legal?
Answer: If the Grid organization receives from the applicant a refusal to sign an agreement due to the fact that it does not comply with the law, the Grid organization is obliged to bring the draft agreement into compliance with the Technological Connection Rules within 5 working days from the date of receipt of such a request and submit a new version to the applicant draft agreement for signing. The refusal of the Network organization in such a situation is unlawful.

4. Question: I submitted an application for technological connection of a 4 kW facility to the Network Organization. For 3 months I constantly called the Network Organization and received the same answer: “Your application is under review.” After I contacted the Network Organization’s website, I received an answer stating that the processing time for applications for the issuance of technical specifications is up to 40 days, but due to the workload of specialists, the terms may be increased. Ultimately, they refused to issue me technical specifications due to the overload of the substation.
Answer: The network organization was obliged to send you a completed and signed draft agreement and technical conditions no later than 30 days from the date of receipt of your application. The actions of the Network Organization to delay sending you the specified documents are unlawful.
In addition, the Grid Organization does not have the right to refuse you to make a technological connection due to the workload of the substation. You have the right to appeal the actions of the Network Organization in accordance with the established procedure.

5. Question: I cannot get consent from my neighbor to connect to the power line, which he partially pulled, since he demands a considerable amount. Does the state somehow regulate this issue, what amount can it ask from us?
Answer: You are not required to obtain consent from your neighbor to connect to the power line that he partially pulled. You must submit an application for technological connection to the Network Organization. The network organization is obliged to independently resolve all issues with indirect connection through your neighbor’s facilities. If the Network Organization is unable to resolve issues with your neighbor, it is obliged to carry out technological connection in another way.
Moreover, if the power you connect is up to 15 kW inclusive, you pay no more than 550 rubles.
Your neighbor has no right to demand that you pay him money. If the technological connection is carried out indirectly, through the facilities of your neighbor, he will not have the right to interfere with the flow of electrical energy and will not have the right to demand payment for this. If the owner of electric grid facilities through which indirect technological connection is made wishes to receive a remuneration for this, he must contact the regulatory tariff authority, which will set a tariff for the services provided. At the same time, he will be assigned all the obligations that are imposed by law on a network organization.
This conclusion follows from the Rules for non-discriminatory access to services for the transmission of electrical energy, the Rules for technological connection, approved by Decree of the Government of the Russian Federation of December 27, 2004 No. 861.

6. Question: Does the network organization have the right to demand that I pay for the technological connection (this was the demand of the employees of the client department) before I receive the draft agreement on technological connection and the draft technical conditions?
Answer: The network organization does not have the right to require you to pay for technological connection before you receive the draft agreement and technical conditions, since the agreement has not yet been concluded with you. The agreement on technological connection is considered concluded from the moment the Grid Organization receives the agreement signed by the applicant. Only after this do you have obligations to pay for the technological connection.

7. Question: The Director of the Grid Organization signed my application for technical conditions for connecting a 3 kW facility and sent me to the LLC company with the words “he will solve all other issues.” The LLC company entered into an agreement with me to carry out design work and an agreement to carry out installation work and their approval. The total cost of work under the contracts is more than 60,000 rubles. Are the actions of the Network Organization and LLC legal?
Answer: The applicant independently determines which organization will carry out design and installation work within the boundaries of its site (of course, by agreement with such an organization and in the event that such work needs to be carried out). Design and installation work for the applicant can be performed by any organization that is engaged in these types of activities. If the Network Organization imposes on the applicant a specific company that will perform design and installation work for the applicant, such actions are unlawful. For coordinated actions of the Network Organization and other persons that lead to restriction of competition and infringement of the interests of consumers of technological connection services, the antimonopoly legislation establishes the most stringent liability.

8. Question: I need to connect an 8 kW facility to electrical networks. Are the actions of the Network Organization legal, which requires me to pay the cost of technological connection in the amount of 4,400 rubles, plus VAT, at the rate of 550 rubles. for every kW of power?
Answer: The actions of the Network Organization are illegal. In this case, the cost of technological connection as a whole should not exceed 550 rubles. Moreover, if you are an individual, VAT is already included in this price.

9. Question: The distance from the border of my land plot to the nearest support of the Network organization is about 6 meters, and the declared maximum power is 5 kW.
When submitting an application for technological connection, I was asked to use a standard modular scheme. In response to my remark, the representative of the Network Organization replied that the approved schemes would come later and this issue would be resolved at the stage of preparing the contract and technical specifications.
Later, I was called to the office of the Network Organization with an offer to familiarize myself with the draft agreement and urgently sign it.
The contract was not presented in full; the contract lacked technical conditions. In addition, the contract contains requirements for me to provide the Grid Organization with permission from Rostechnadzor to allow the power installation of a residential building to operate. In addition, in the presented draft agreement, I am offered technological connection according to an individual project.
Are the actions of the Network Organization legal?

Answer: The network organization committed a set of violations:
1) standard modular schemes for technological connection must be approved by the Ministry of Energy of the Russian Federation. They are not currently approved. Consequently, the Network Organization does not have the right to require you to submit a modular diagram and does not have the right to refuse you technological connection due to their failure to provide it;
2) The network organization does not have the right to demand urgent (immediate) signing of the draft agreement by you. You have the right to sign it within 30 days from the date of receipt of the completed and signed agreement by the Network Organization;
3) the contract must contain technical conditions;
4) to connect power plants of your residential building, the power of which is 5 kW, it is not necessary to obtain permission from Rostekhnadzor for admission to operation;
5) technological connection in your case is carried out in a general manner, and not according to an individual project (the power of the power plant is 5 kW).

10. Question: I have submitted an application to connect an 8 kW facility. According to the technical specifications received, I must install a 038 kV overhead line from RU-04kW GKTP-175 along existing supports to the facility. To obtain a Certificate of delineation of balance sheet ownership and a Certificate of technological connection, I must present an act of admission to operation of power receiving devices, obtained from Rostechnadzor. In design organizations, the cost of a certificate from Rostechnadzor is about 15 thousand rubles.
Are the actions of the Network Organization legal?

Answer: the actions of the Network Organization are illegal:
1) The network organization is obliged to carry out all activities up to the boundaries of your land plot and does not have the right to impose obligations on you to lay power lines to your land plot;
2) The grid organization is obliged to sign with you an act of delimitation of balance sheet ownership and an act of technological connection. At the same time, the Network Organization does not have the right to require you to submit permission from Rostechnadzor to allow the power receiving device into operation and to require you to pay money.